之間的兩塊焊接網(wǎng)、較小的鋼筋搭接長(zhǎng)度不應(yīng)小于1.3倍較小的錨固長(zhǎng)度,和不應(yīng)小于200毫米的搭接區(qū),每個(gè)焊接網(wǎng)片橫向鋼筋不應(yīng)小于1,兩個(gè)鋼絲網(wǎng)片的橫向鋼筋間距不應(yīng)小于50毫米。
The overlapping length of the last two welded meshes and the smaller reinforcement shall not be less than 1.3 times of the smaller anchoring length, and the overlapping area shall not be less than 200 mm. The transverse reinforcement of each welded mesh shall not be less than 1, and the spacing between the transverse reinforcement of the two steel mesh shall not be less than 50 mm.
搭接區(qū)域有一個(gè)無(wú)橫向鋼筋的鋼網(wǎng)片時(shí),加筋鋼網(wǎng)片的較小搭接長(zhǎng)度應(yīng)是較小錨固長(zhǎng)度la的1.3倍,且不應(yīng)小于300mm。當(dāng)搭接區(qū)域縱向受力鋼筋直徑d≥10mm時(shí),搭接長(zhǎng)度應(yīng)增加5d。
When there is a steel mesh without transverse reinforcement in the overlapping area, the smaller overlapping length of the reinforced steel mesh shall be 1.3 times of the smaller anchoring length La, and shall not be less than 300 mm. When the diameter of the longitudinal stressed reinforcement in the overlapping area D ≥ 10 mm, the overlapping length shall be increased by 5 days.
今后鋼網(wǎng)設(shè)備的檢驗(yàn)方法:鋼網(wǎng)鋪裝的主要工序是:鋼網(wǎng)焊接后應(yīng)按設(shè)計(jì)圖紙定位——網(wǎng)片設(shè)備——網(wǎng)片檢驗(yàn)。補(bǔ)強(qiáng)鋼網(wǎng)的一級(jí)配筋是:設(shè)備底網(wǎng)-附加墊網(wǎng)或補(bǔ)強(qiáng)設(shè)備-承重面網(wǎng)鋪-水平和水平面網(wǎng)鋪-附加網(wǎng)和補(bǔ)強(qiáng)設(shè)備。
Inspection method of steel mesh equipment in the future: the main process of steel mesh pavement is: after the steel mesh is welded, it should be positioned according to the design drawings - mesh equipment - mesh inspection. One grading reinforcement of steel mesh reinforcement is: equipment bottom net - Additional mat net or reinforcement equipment - bearing surface net - horizontal and horizontal surface net - additional net and reinforcement equipment.

在網(wǎng)架的底部,左右要注意主筋應(yīng)放在擋塊的底部,當(dāng)網(wǎng)架的主筋左右放在擋塊的頂部。當(dāng)兩個(gè)相鄰的網(wǎng)格存在重疊時(shí),在重疊區(qū)域的和兩端應(yīng)選擇鋼絲綁扎牢固,綁扎點(diǎn)不小于3。附加的鋼筋和焊接網(wǎng)的每個(gè)接頭都由鐵絲綁扎而成。
At the bottom of the grid, the left and right main reinforcements should be placed at the bottom of the block, when the main reinforcements of the grid are placed at the top of the block. When there is overlap between two adjacent grids, steel wire shall be selected at the center and both ends of the overlapping area to bind firmly, and the binding point shall not be less than 3. Each joint of additional reinforcement and welded mesh is bound by iron wire.